Grand Ledge Public Schools Facilities Management Plan
Updated automatically every 5 minutes

Facilities Management Plan

Buildings, Technology Device and Infrastructure, Athletics Facilities, Heavy Equipment

2024-2027


Table of Contents

Introduction

Definition of Terms

Personnel

Strategic Plan

Buildings

Delta Center

Holbrook

Wacousta

Willow Ridge

Hayes

Beagle

Grand Ledge High School

Grand Ledge High School - Fine Arts

Grand Ledge High School - Auditorium

Delta Mills ECC

Neff ECC

Sawdon

Operations / Transportation

Technology Devices and Infrastructure

Athletic Facilities

Heavy Equipment


Introduction

Grand Ledge Public Schools is a large, mid-Michigan school district with approximately 5300 students and 700 staff members. Comprised of seven K-12 buildings, two early childhood centers, an operations center, and administration building, along with numerous athletic and activity fields, the district spans approximately 125 square miles in three counties. GLPS’s most recent upgrades have come from a 2018 bond proposal, which reshaped the district’s grade level bands, added facilities in multiple categories, and upgraded infrastructure. In addition, GLPS has a sinking fund, which is used for regular improvements.

This document serves as a record of needs, initiatives, and plans, and serves as a way to document priorities for upgrades and replacements, guided by the district’s strategic plan. It is important to note that this is a living document. As needs, costs, and realities change, the document will be updated. The revision date will always be included as a footer on each page, in order to ensure that stakeholders understand the ongoing nature of facilities management work. Not all boxes will always be filled in as needs, funding sources, and available information changes.

District leaders, including the superintendent; deputy superintendent; student safety supervisor; executive director for technology; athletic director; maintenance, grounds, and custodial supervisor; bond supervisor; and chief financial officer, met monthly throughout the 2023-2024 school year to create the initial draft, and it was shared with the board of education in July of 2024. The plan, moving forward, is for that team to meet on a regular basis to update the document. Community and stakeholder input is welcomed, and should be shared via regular communication methods with the leaders listed above.

Ultimately, the document serves as a record of needed upgrades and updates, and it will assist in budget planning moving forward.


Definition of Terms

Minimum Value - Facility or equipment upgrades that exceed $5000 are included in this plan. Any upgrades that fall below the threshold are viewed as regular maintenance items.

Costs - Costs will be updated annually for inflation, and are based on best estimates or quotes from vendors.

Budget Sources - Budget sources will be updated in the document as purchases approach, because of the nature of state budgets and voter approved revenue sources.

Priorities - Priorities for funding will be based on the district strategic plan, as well as answers to the following questions, in order:

  1. Does this cut/add violate a collective bargaining agreement, board policy, or other law or requirement?
  2. Does this cut/add directly impact students or student programming?
  3. Does this cut/add impact adults who directly impact students or student programming?
  4. Does this cut/add impact the ease with which adults do their work, but does not fall into the category of number 2 or number 3 above?

This means that there may be items on the list that get pushed to a later date, based on available funding.


Personnel

The following individuals represent the team that is responsible for the development and implementation of this plan:


Strategic Plan

Strategic Plan Goals

Buildings


Delta Center

Name

Purpose

Last Upgrade

Needed Upgrades

Cost of Needed Upgrades

Timeline for Needed Upgrades

Budget Source for Needed Upgrades

Boiler

Heating Building

2023

Replacement

$50,000-$60,000/per boiler X 2

2033/2035

Domestic Hot Boiler

Hot Water

2012

Replacement

$8,000-$10,000

2025/2030

General Fund Operations

Roofing

Old&Leaking

1987  100 hallway

Replacement

Direct layover $10.65 sq ft Tear off $18.50

2025 to 2035

Roofing

Old&Leaking

1992 300 hallway

Replacement

Direct layover $10.65 sf ft Tear off $18.50

2030/2035

Roofing

Old&Leaking

2010 200 hallway

Replacement

Direct layover $10.65 sq ft Tear off $18.50

2040/2045

Roofing

Old Past it’s life span

2020 roofing main office, main office hall, media center

Replacement

Direct layover $10.50 sq ft Tear off $18.50

2050/2055

A/C Compressor

Cooling building

2010

Replacement

$8,000-$12,000 X 2

2025/2030

General Fund Operations

Controls on the front end of the change aires

Regulates heating and cooling

2010

Replacement

$88,000

When funding is available?

LED Upgrades/Indoor/outdoor

Energy efficient

1980’s

 Replacement

$385.00 per fixture

$585.00 per fixture with battery. 34 weeks lead time, includes installation

When funds are available?

Carpet replacement

Old, ripped

2000”s

Replacement

$4,100 per avg classroom

When funds are available?

Painting classroom and hallways

Needs a fresh layer of paint

2023 main hall/new wing

300 hall 2008

Rest of the building?

Re-Paint

$.80 cents a square foot

When funds are available?

3M Security Film on entry point doors / windows

Strengthening / “hardening” of our entry points

Unknown

New

About $20 per square foot.

As funds are available.

School Safety Grants

Perforated vinyl window graphics

Concealment of entry points

N/A

New

$274 - $299 per 43.5 x 74 inch window

As funds are available, then replace every  7 to 10 years

School Safety Grants

Holbrook

Name

Purpose

Last Upgrade

Needed Upgrades

Cost of Needed Upgrades

Timeline for Needed Upgrades

Budget Source for Needed Upgrades

Holbrook

Heating building

2020

Replacement

$50,000-$60,000/ per boiler X 2

2030/2035

Holbrook

Hot Water

2013

Replacement

$8,000-$10,000

2023/2027

General Fund Operations

Roof

Old past its life span

2015   Rm # 300 to 400 hallway area

Replacement

Direct layover $10.65 sq ft Tear off $18.50

2035/2040

Roof

Old past its life span

2020 Rm# 100 and 200 hallway area

Replacement

Direct layover $!0.65 sq ft Tear off $18.50

2045/2050

A/C  Chiller Compressor

Cooling Building  

2020

Replacement

$10,000-$14,000 X 2

2030/2035

Carpet Replacement

Old, ripped

2019

replacement

$4,100.00 per avg classroom

2035/2040

Painting hallways/classrooms

Needs a fresh layer of paint

2019

Re-paint

$.80 cents per square foot

2035/2040

3M Security Film on entry point doors / windows

Strengthening / “hardening” of our entry points

Unknown

New

About $20 per square foot.

As funds are available.

School Safety Grants

Perforated vinyl window graphics

Concealment of entry points

N/A

New

$274 - $299 per 43.5 x 74 inch window

As funds are available, then replace every  7 to 10 years

School Safety Grants

Wacousta

Name

Purpose

Last Upgrade

Needed Upgrades

Cost of Needed Upgrades

Timeline for Needed Upgrades

Budget Source for Needed Upgrades

2 Boilers

Heating the building

2024

Replacement

$50,000-$60,000/per boiler X 2

2034/2039

Roof

Roof replacement

2024

Replacement

2054/2059

Parking lot

potholes

2024

Replacement

$298,000

2049/2055

Domestic Hot water

Potable Hot water

2024

Replacement

$5,000-$8,000 per unit X 2

2034/2038

General Fund Operations

INDV cooling compressors per room

Cooling Classrooms

2024

Replacement

$3,000 per classrooms X 25

2034/2040

Carpeting

Classroom and Hallway

2024

Replacement

$4,100 per average room

2035/2040

3M Security Film on entry point doors / windows

Strengthening / “hardening” of our entry points

Unknown

New

About $20 per square foot.

As funds are available.

School Safety Grants

Perforated vinyl window graphics

Concealment of entry points

N/A

New

$274 - $299 per 43.5 x 74 inch window

As funds are available, then replace every  7 to 10 years

School Safety Grants


Willow Ridge

Name

Purpose

Last Upgrade

Needed Upgrades

Cost of Needed Upgrades

Timeline for Needed Upgrades

Budget Source for Needed Upgrades

2 Boilers

Heating the building

2025

Replacement

$50,000 - $60,000/per boiler X 2

2040

Domestic hot boiler

Hot Water

2014

Replacement

$8,000-$10,000

2023/2027

General Fund Operations

Chiller

Cooling building

2025

Replacement

$150,000

2045

Roofing

Old & Leaking

1997

Replacement

Direct layover $10.65 sq ft Tear off $18.50

2030/2035

Parking lot repair

Potholes

2025

Replacement

$300,000

2045

LED lighting Indoor/Outdoor

Energy efficient

1997

Replacement

$385 per fixture $585 w/ battery. 34 week lead time. Price includes install

As funds are available.

3M Security Film on entry point doors / windows

Strengthening / “hardening” of our entry points

Unknown

New

About $20 per square foot.

As funds are available.

School Safety Grants

Perforated vinyl window graphics

Concealment of entry points

N/A

New

$274 - $299 per 43.5 x 74 inch window

As funds are available, then replace every  7 to 10 years

School Safety Grants

Hayes

Name

Purpose

Last Upgrade

Needed Upgrades

Cost of Needed Upgrades

Timeline for Needed Upgrades

Budget Source for Needed Upgrades

3 Boilers

Heating the Building

2025

Replacement

$65,000-$70,000/ per boiler x 3

2035/2040

 2 Hot water Heater

Domestic hot water

2014

Replacement

$8,000-$10,000 per unit X 2

2030/2035

General Fund Operations

Roof Cafeteria area

Replace roof partial

2025

Partial roof replacement

Tear off $18.50 sq ft

2055

 

2 small AHU’s

Heating/Cooling office/cafe

2025

Full Replacement

$40,000 each

2050

2 Large AHU’s

Heating/Coolingband/ choir,counseling

2025

Full Replacement

$75,000 each

2050

Pumps/Motors

Heating

2025

Full Replacement

$10,000 each

2045

Water softener

Softening the water

1997

Full

Replacement

$15,000

2025/2030

LED lighting parking lot

Energy efficient

1997

Partial replacement

$10,000

When funds are available

Painting: hallway and classrooms

Fresh layer of paint

2025 partial

Re-paint

$.80 cents per foot

When funds are available

Carpet

Class rooms has hard tile surface

2025 partial 13 rooms have carpet

Replacement

$4,100.00

When funds are available

Bathroom upgrades

Old fixture and tile

1997

Full replacement

$50,000/$100,000 per bathroom

When Funds are available

Roof Replacement

Old, time to replace

1993,1997,2010

Replacement

Direct layover $10.65 Tear off $18.50

2030/2035

3M Security Film on entry point doors / windows

Strengthening / “hardening” of our entry points

Unknown

New

About $20 per square foot.

As funds are available.

School Safety Grants

Perforated vinyl window graphics

Concealment of entry points

N/A

New

$274 - $299 per 43.5 x 74 inch window

As funds are available, then replace every  7 to 10 years

School Safety Grants


Beagle

Name

Purpose

Last Upgrade

Needed Upgrades

Cost of Needed Upgrades

Timeline for Needed Upgrades

Budget Source for Needed Upgrades

3 Boilers

Heating the Building

2020

Replacement

$70,000-$80,000 per unit X3

2030/2035

1 Pool Boiler

Heating the Pool water

2021

Replacement

$40,000-$50,000

2030

Roofing Rm #200-215

Old & Leaking

2007

Replacement

Direct Layover $10.65 Tear off $18.50 sq ft

2037/2042

Roofing over Cafeteria & Kitchen

Old&Leaking

2007

Replacement

Direct Layover $10.65 sq ft

Tear off $18.50

2037/2042

Roof Aux Gym

Old&Leaking

2007

Replacement

Direct Layover $10.65 sq ft Tear off $18.50

2037/2042

Rest of the roof

New Addition

2020

Replacement

Direct Layover $10.65 sq ft Tear off $18.50

2055/2060

Chiller Compressors

Cooling

2010

2020

Replacement

Replacement

$12,000-$16,000 X 4

2025/2030

2030/2035

1 Domestic hot water Kitchen

Potable Hot water

2008

Replacement

$8,000-$10,000

2025/2030

General Fund Operations

3 Domestic hot water Building

Potable Hot Water

2020

Replacement

$8,000-$10,000per unit X3

2030/2035

General Fund Operations

1 Pool Chiller

Cooling the pool

2020

Replacement

$12,000-$16,000 X 2

2035

General Fund Operations

3M Security Film on entry point doors / windows

Strengthening / “hardening” of our entry points

Unknown

New

About $20 per square foot.

As funds are available.

School Safety Grants

Perforated vinyl window graphics

Concealment of entry points

N/A

New

$274 - $299 per 43.5 x 74 inch window

As funds are available, then replace every  7 to 10 years

School Safety Grants


Grand Ledge High School

Name

Purpose

Last Upgrade

Needed Upgrades

Cost of Needed Upgrades

Timeline for Needed Upgrades

Budget Source for Needed Upgrades

3 Hydronic boilers

Heating the building

2024/2025

 

2040/2041

1 pool boiler

Heating pool water

2021

Replacement

$30,000-$40,000

2031/2035

General Funds Operations

All classroom univents

Heating Classrooms

2025

Replacement

2050

 3- 350 ton chillers

Cooling of High School

2025

Replacement

2045

2- Domestic boilers hot water

Domestic hot water

2024

Replacement

$30,000- $45,000

2039

2 Heating units in Auxiliary gym

Heating and Cooling

2025

Replacement

2045

Roofing

Ballast roofs

2025

Replacement

$975,000

2065

Pool resurfaced

Pool walls and floor

1997

Full  resurface

$170,000

2024-2026

Sinking fund

LED Upgrades

Energy Efficient

1980’s

Replacement from Fine Arts to the North

$385 per fixture $585 per fixture w/ battery. 34 weeks lead time includes install

When funds are available

Roofing Aux gym, New gym, Aud,Math,pool area

Aged, old

1997

Replacement or layover

Direct layover $10.65 Tear off $18.50

2030/2035

Bathroom upgrades

Aged

1958-2010

Full Replacement

$50,000/100,000 per bathroom

2024/Present

3M Security Film on entry point doors / windows

Strengthening / “hardening” of our entry points

Unknown

New

About $20 per square foot.

As funds are available.

School Safety Grants

Perforated vinyl window graphics

Concealment of entry points

N/A

New

$274 - $299 per 43.5 x 74 inch window

As funds are available, then replace every  7 to 10 years

School Safety Grants

Cut Outs and Handicap Spaces

Create a more inclusive experience at the stadium

NA

Additional access

Bus Loop Resurfacing

Repair cracks and potholes

Unknown

Resurfacing

SInking Fund


Grand Ledge High School - Fine Arts

Name

Purpose

Last Upgrade

Needed Upgrades

Cost of Needed Upgrades

Timeline for Needed Upgrades

Budget Source for Needed Upgrades

2 Boiler

Heating the building

2024

Replacement

$50,000-$60,000 X 2

2033/2038

Roofing

2025

Replacement

Direct layover $10.65 Tear off $18.50 sq ft

2055/2060

Domestic Hot water Boiler

Potable Hot Water

2024

Replacement

$5,000-$8,000

2035/2038

General Funds Operations

Perforated vinyl window graphics

(19 windows)

Concealment of band room

N/A

New

$5,190 - $5,680

As funds are available, then replace every  7 to 10 years

School Safety Grants

3M Security Film

(19 windows)

Option for safety enhancement of band room

N/A

New

$8,710

As funds are available.

School Safety Grants

3M Security Film on entry point doors / windows

Strengthening / “hardening” of our entry points

Unknown

New

About $20 per square foot.

As funds are available.

School Safety Grants

Perforated vinyl window graphics

Concealment of entry points

N/A

New

$274 - $299 per 43.5 x 74 inch window

As funds are available, then replace every  7 to 10 years

School Safety Grants

Grand Ledge High School - Auditorium

Name

Purpose

Last Upgrade

Needed Upgrades

Cost of Needed Upgrades

Timeline for Needed Upgrades

Budget Source for Needed Upgrades

Auditorium Seats

1995

Replacement


Delta Mills ECC

Name

Purpose

Last Upgrade

Needed Upgrades

Cost of Needed Upgrades

Timeline for Needed Upgrades

Budget Source for Needed Upgrades

1 Boiler new 2 Boilers old

Heating the building

1 boiler is 2023

2 boilers early 80’s

Replacement

$60,000

2024

Sinking Fund

Roof

Old & leaking

2016

Replacement

Tear off $18.50 sq ft

2036

2 Hot water heater

Potable hot water

2016

Replacement

$5,000  X 2

2025/2030

General Fund Operations

3M Security Film on entry point doors / windows

Strengthening / “hardening” of our entry points

Unknown

New

About $20 per square foot.

As funds are available.

School Safety Grants (or other means due to potential grant stipulations)

Perforated vinyl window graphics

Concealment of entry points

N/A

New

$274 - $299 per 43.5 x 74 inch window

As funds are available, then replace every  7 to 10 years

School Safety Grants (or other means due to  potential grant stipulations)


Neff ECC

Name

Purpose

Last Upgrade

Needed Upgrades

Cost of Needed Upgrades

Timeline for Needed Upgrades

Budget Source for Needed Upgrades

2-Boilers

Heating building

2024

Replacement

$718,000

2039

Domestic Hot water boiler

Hot water

2013

Replacement

$5,000/$8,000

2024/2027

General Fund Operations

Roof Replacement

Replacement

2024

Entire roof upgraded

$600,000

2060

A/C Compressors

Cooling

2010

Replacement

$8,000-$12,000 X 2

2025/2027

General Fund Operations

Water Softener

Soften water

2015

Replacement

$5,000/$8,000

2030

LED Upgrades

Parking lots and wall packs

Energy Efficient

2021

Partial Replacement

$385 per fixture $585 per fixture w/ battery. 34 weeks lead time. Includes install

3M Security Film on entry point doors / windows

Strengthening / “hardening” of our entry points

Unknown

New

About $20 per square foot.

As funds are available.

School Safety Grants (or other means due to  potential grant stipulations)

Perforated vinyl window graphics

Concealment of entry points

N/A

New

$274 - $299 per 43.5 x 74 inch window

As funds are available, then replace every  7 to 10 years

School Safety Grants (or other means due to  potential grant stipulations)

Carpet

Class rooms and offices

Replacement

$4,100.00

When funds are available

Sawdon

Name

Purpose

Last Upgrade

Needed Upgrades

Cost of Needed Upgrades

Timeline for Needed Upgrades

Budget Source for Needed Upgrades

2 boiler replacements

Heating the building

1-2014 boiler

1-2018 boiler

Replacement

Replacement

$60,000 / $ 65,000 per boiler  X 2

2024/2026

2028/2030

First Floor cooling North End

Cooling Special services, Business office

2024

Replacement

$75,000

2045

Second floor cooling North End

Cooling technology

2024

replacement

$75,000

2045

Roofing Gymnasium

Old &Leaks

Replacement

Direct layover $10.65 sq ft Tear off $18.50

2030/2035

3rd floor roofing over classrooms

Old & Leaks

Replacement

Direct layover $10.65 sq ft Tear off $18.50

2035/2040

Roofing ACR room

Old & Leaks

2010

Replacement

Direct layover $10.65 sq ft Tear off $18.50

2045/2050

Hallways/roofing H.R & Academics

Old and Leaks

1997

Replacement

Direct layover $10.65 sq ft Tear off $18.50

2035/2040

LED upgrades

Energy Efficient

2023

Replacement

$385 per fixture

$585 per fixture w/battery. 34 weeks lead time. Includes install

When funds are available

Data Center UPS

Backup Power

2022?

Replacement

Data Center Climate Control

Data Security

2023?

Replacement

3M Security Film on entry point doors / windows

Strengthening / “hardening” of our entry points

Unknown

New

About $20 per square foot.

As funds are available.

School Safety Grants

Perforated vinyl window graphics

Concealment of entry points

N/A

New

$274 - $299 per 43.5 x 74 inch window

As funds are available, then replace every  7 to 10 years

School Safety Grants


Operations / Transportation

Name

Purpose

Last Upgrade

Needed Upgrades

Cost of Needed Upgrades

Timeline for Needed Upgrades

Budget Source for Needed Upgrades

2 Inline heaters

Heating the wash bay

2025

Replacements

2045

3 Existing Door Heater for the Mechanics Bays

Heating the bays when doors are open

2025

Replacement

2050

Main Heating AHU

Heating the rest of mechanics shop

2025

Refurbish and/or full replacement

2050

Bus Loop Curbing

Old and deteriorating

2025

Replacement

2050

LED Lighting

Energy Efficient

2020

Partial Replacement

When funds are available

Salt Barn

Renting Space

None

New

$100,000

When funds are available

Radios / Antenna / Batteries (school radios)

Direct Communication for staff / admin.

Ongoing

(225 total radios so far within district)

Radios / Antenna / Batteries

$339 per SR24 radio

$22 per antenna

$49.95 per battery

 Varies - 3 to 5 yrs

Operations / School Safety Grants

Midland WR400

  (13 units)

Weather radios for buildings

Unknown

New / Replacements

Total cost = $975

As funds are available.

School Safety Grants

3M Security Film on entry point doors / windows

Strengthening / “hardening” of our entry points

Unknown

New

About $20 per square foot.

As funds are available.

School Safety Grants (or other means due to  potential grant stipulations)

Perforated vinyl window graphics

Concealment of entry points

N/A

New

$274 - $299 per 43.5 x 74 inch window

As funds are available, then replace every  7 to 10 years

School Safety Grants (or other means due to  potential grant stipulations)

Technology Devices and Infrastructure

Name

Purpose

Last Upgrade

Needed Upgrades

Cost of Needed Upgrades

Timeline for Needed Upgrades

Budget Source for Needed Upgrades

Staff iPads

Staff iPads

2020-2021

Replacement

200,000

Spring 2027

Staff Computers

Staff Computers

2021-2022

Replacement

680,000

Spring 2027

Servers

Servers

2021-2022

Replacement

120,000

2026-2027

2026-2027 Total

1,000,000

Student Computers

Student Computers

2022-2023

Replacement

250,000

Spring 2028

Wireless

Network

2022-2023

Replacement

400,000

2027-2028

Switches

Network

2022-2023

Replacement

425,000

2027-2028

2027-2028 Total

1,075,000

High School Chromebooks

Student Chromebooks

2023-2024

Replacement

600,000

Spring 2029

Firewall

Network Security

2023-2024

Replacement

30,000

2028-2029

Camera Servers

Security

2023-2024

Replacement

90,000

2028-2029

2028-2029 Total

720,000

Student iPads

Student iPads

2024-2025

Replacement

650,000

2029-2030

General Fund

Apple TVs

Apple TVs

2024-2025

Replacement

60,000

2029-2030

General Fund

Copiers

Copiers

Replacement

500,000

2029-2030

UPSs

UPSs

Replacement

110,000

2029-2030

2029-2030 Total

1,320,000

Elementary Chromebooks

Student Chromebooks

March 2021

Replacement

370,000

Spring 2031

Intermediate & Middle Schools Chromebooks

Student Chromebooks

July 2021

Replacement

630,000

Spring 2031

Staff Chromebooks

Staff Chromebooks

July 2021

Replacement

60,000

Spring 2031

2030-2031 Total

1,060,000

Security Cameras

Security

Varies

Replacement

375,000

2030-2031

Projectors

Projectors

Varies

Replacement

625,000

2034-2035

Athletic Facilities

Name

Purpose

Last Upgrade

Needed Upgrades

Cost of Needed Upgrades

Timeline for Needed Upgrades

Budget Source for Needed Upgrades

New Addition Branding

Directions, Community Pride, Program promotion

Never

New purchase

Spring/Summer 2024

Weight Room Record Board

Motivational/Spirit/Pride

Never

New purchase

Spring/Summer 2024

New Switch System for HS Main and Aux Gym Basketball Hoops

We need a better system to take stress off equipment

30 years

Replacement

Get quote

2025

Replace and/or adjust West bleachers in HS Main Gym

Safety - fans must walk through the stands to enter bleachers

25 years

Replacement

Get quote

As soon as funds are available

Install Fence to include the sidewalk on the North end of the stadium

Safety - Less congestion of fans getting to/from their seats

Never

New purchase

As soon as funds are available

Stadium Fencing Improvements

Curb Appeal for our district at a facility that is used constantly and visible to everyone

Mid 1990’s

New fencing

Get quote

As soon as funds are available

LED Board at Stadium

Move scoreboard to visible area not facing sun - promote student broadcast work; promote district; promote events

November 2025

$170,000

2024-2025

Funds assigned within capital projects fund

Main Gym Sound System

Music and announcements at events

August 2025

New system

Completed

Siding Improvements - Beagle Dugout

Current siding it broken and worn down

Unknown

New siding

As soon as funds are available

Replace Tennis Barn with Pre-Fab Barn w/overhead door

Tennis barn is constantly broken into and it needs to be bigger and have easier access.

August 2024

New barn

Completed

Summer of 2054

Softball Scoreboard

Difficult to read, constant bulb replacement, remote entry

August 2025

New scoreboard

$30,000

Completed

Summer of 2045

Fixing Serving Windows at Stadium Concessions

Stadium concessions

Original to the mid 90s stadium renovation

New frames and screens

Get quote

As soon as funds are available

Back Stop Improvements at Gorman

Safety

Scheduled November 2025

Net System - $3,200

Poles - $9,000

Concrete - $4,400

Boom Rental - $1,300

2024-2025

Upgrade to LED Lights at Stadium

Stadium is dark, more efficient, Safety and save money

Mid-90s stadium renovation

New lights

Get quote

As soon as funds are available

New Scoreboards in High School Main Gym

Bulbs constantly need replaced; Parts nearly impossible to come by due to age; Accessibility issues due to hard wired controllers; Controllers difficult to get due to age

April  2025

New scoreboard

15-17,000 EACH

As soon as funds are available

Tennis Court Resurface/Fix

Safety - cracks continue to get bigger

Partial repair August 2025

Resurfacing and eventual full replacement

Get quote for full replacement

As soon as funds are available

Irrigation System at Gorman Baseball

Not working

Not known

New system

Get quote

As soon as funds are available

Gym Floor Replacement at HS Aux and main Gym

Old, slippery, doesn’t look good

Original

repair/replace

Get quote

As soon as funds are available

New Floor Markings for PE Staff at Beagle Aux Gym

Needed for effective PE curriculum

Original

New markings

As soon as funds are available

Additional parking at track facility

Additional parking needed

Original

More spaces

Depends on spaces needed

As soon as funds are available

Sidewalk and Pad on East side of Track

Complete the facility

Original

Meet management

$60,000

As soon as funds are available

Community Pool Resurfacing

Needs upgrades to floor

2007

Replace enamel

$200,000

Spring/Summer 2026

Sinking Fund


Heavy Equipment

Name

Purpose

Last Upgrade

Needed Upgrades

Cost of Needed Upgrades

Timeline for Needed Upgrades

Budget Source for Needed Upgrades

Dump Truck

Daily use for grounds staff

Sold 2 years ago

New purchase

$83,000

2024-2025

Operations Budget

 ¾ ton work truck

Daily use for grounds

New purchase

$50,000

2024-2025

Operations Budget

1 ton work truck

Daily use for grounds

New purchase

$60,000

2024-2025

Operations Budget

New salter for Dump truck

Winter use

New purchase

$12,000

2024-2025

Operations Budget

Lawn mower

Daily use summer

New purchase

$15,000

2024/annually

Operations Budget

Bus Replacement

Annual need

Annual need

Annual need

$140,000/bus

Annually

Vehicle(s) Replacement

District use

Replacement

Food Service Truck

Food transportation

Replacement

Box Truck

District use

Replacement

Van(s)

District use

Replacement

Instrumental Music

Name

Purpose

Last Upgrade

Needed Upgrades

Cost of Needed Upgrades

Timeline for Needed Upgrades

Budget Source for Needed Upgrades

Last Updated: 9/11/25